Erection drawings for structural steel

Erection drawings show the site team where every piece of steel goes, which way round, and in what order. What they contain, who uses them, and how they differ from GA and fabrication drawings.

Published 4 min read

What erection drawings are

Erection drawings are the steelwork drawings made for site. Once the steel has been fabricated and delivered, the erection team needs to know which piece is which, where it goes and how it connects. Erection drawings answer those questions, using the same assembly marks that were painted or stamped on each piece in the shop.

You will also hear them called erection layouts, marking plans or erection GAs. On a small job they may simply be the approved GA drawings with erection marks added. On a larger one they are a separate set, often split by phase.

What they show

  • Plans and elevations on the building grid, with every assembly mark in position.
  • Orientation: which end of a beam goes where, and which way a column faces.
  • Bolt information at each connection: size, grade and quantity.
  • Levels and setting-out for the steel, tied back to the holding-down bolt plan.
  • 3D views of awkward areas, so the erectors can see how the pieces come together.
  • Phase or sequence information, where the job goes up in stages.
  • Notes on site welds, site drilling and anything else that has to be done on site rather than in the shop.
3D erection view of a steel frame with grid lines and marks
A 3D erection view with grid lines and marks, showing how the frame goes together before it arrives on site.Drawing

Marks and orientation

Every shipping piece carries an assembly mark. Erection drawings place each mark on the grid and show which way round it goes, often with a marker at one end, so a beam isn't hung back to front or a column turned the wrong way. Mistakes like that are a common cause of re-work on site, and they are cheap to prevent on paper.

Who uses them

  • The erection supervisor and crew, who place and bolt up each piece.
  • The site manager and main contractor, planning deliveries, crane positions and progress.
  • The fabricator's dispatch team, loading wagons in the order the steel will go up.
  • Other trades checking where their work meets the frame.

What erection drawings don't cover

Erection drawings vs GA drawings

A GA drawing is drawn for approval and coordination; the erection drawing is drawn for the people putting the steel up. They share the same plans and elevations, but the erection drawing leaves out what site doesn't need and adds what it does: marks, orientation, bolts and sequence. The GAs are approved first, and erection drawings follow once the design is settled.

Erection drawings vs fabrication drawings

Fabrication drawings describe each piece in full for the workshop: holes, plates, welds and cuts. Erection drawings don't repeat that detail. They treat each fabricated piece as a mark to be placed and connected. Between them, along with the holding-down bolt plans that go out first, they take the steel from the shop floor to its place in the frame.

What SSD issues

Our erection plans come from the same 3D model as the GAs and fabrication drawings, so marks, bolt lists and positions agree across the whole set. We issue marking plans and 3D views showing where every piece goes and in what order, phased to suit your erection sequence, with bolt lists by phase. We stay on the job through erection, turning revisions round and answering site queries. See what drawings we produce or our detailing services.

Common questions

Q01

What is an erection drawing in steel structures?

An erection drawing shows the site team where each fabricated piece of steel goes, which way round, how it connects and in what order, using the assembly mark on each piece.

Q02

Are erection drawings the same as GA drawings?

Not quite. They share the same plans and elevations, but a GA is drawn for approval and coordination, while an erection drawing is drawn for the erection team, with marks, orientation, bolts and sequence.

Q03

Do erection drawings include lift plans?

No. Lift plans are prepared by the appointed person for lifting operations, and temporary works are designed by the temporary works designer. Erection drawings show the permanent steel, its marks and its connections.

Q04

Who uses steel erection drawings?

Mainly the erection supervisor and crew, along with the site manager planning deliveries and crane positions, and the fabricator loading wagons in the order the steel will go up.